PROJECT DETAILS:  Over the last several years, the City has replaced several miles of water transmission main between the new Slow Sand Water Filtration Plant located on NE Lessard Road and the water distribution system that serves our customers. The remaining old section of waterline was installed in the 1920’s and is located between NE 312th /Ireland Road and the new Slow Sand Water Filtration Plant. Camas Engineering Staff are working with CH2M of Portland to complete the design and permitting required to construct the new waterline in 2018.

CONTACT:  Questions about the project may be directed to the Steve Durspek, Project Engineer, at 360.817.7238 or at sdurspek@cityofcamas.us