Load Full Menu

Current and Upcoming Work

NE Everett Street - Single lane closures will continue on Everett Street and progress north to NE 43rd Avenue and Leadbetter Road through August 31st. Drivers will experience longer delays as construction moves north past NE 23rd Ave where NE Everett transitions from 3 lanes to 2 lanes. Drivers should use alternate routes.  Pavement restoration work will take place July 26th and 27th. 

NE 23rd Avenue between Birch and Everett - Construction staging will continue in this area through August.

Lacamas (Round Lake) Park - Expect short term impacts on the south entrance of the trail from July 18th through August 7th due to sewer construction activities. The parking lot will remain open during this time.  The parking lot at Lacamas Park will be closed September 9th-30th due to construction activities. Use the overflow parking lot located on NE 35th Ave.

NE 43rd Avenue - Excavation for a new water line will begin July 10th and continue through July 31st. During this time, NE 43rd Ave between NE Everett and NE Garfield will be CLOSED to all traffic, except local access, Monday through Friday, between 7 a.m.-7 p.m.

232nd Avenue at Camp Currie – Trucks will be entering the roadway at this location due to sewer construction activities beginning July 24th and continuing through August 18th.

232nd Avenue Pump Station – Just south of 9th Street on 232nd Avenue, trucks will be entering the roadway beginning July 25th through August 21st  to begin clearing work to construct the 232nd Avenue Pump Station.  

Updated July 21, 2017

The North Shore Sewer Transmission System Project will construct 4.5 miles of new sewer pipeline to serve the area north of Lacamas Lake, which is expected to see future residential, commercial and light industrial development. The project will also build three new wastewater pump stations and a pedestrian/pipe bridge across the Lacamas Lake and Round Lake channel.

Funding for this $12 million project has been provided through Water and Sewer Revenue Bonds issued by the City. Construction work is being done by Rotschy Inc. of Vancouver, WA.

Construction Map

The construction map below will be updated regularly with anticipated construction activities and impacts. Click on lines and icons to learn about the project. You can turn map elements on and off using the “Layers” menu.

Note: Alignment and marker locations shown are for general reference only and may not match precisely with their actual location on aerial photographs.

Construction

Variable Message Sign.

Construction in many areas will require limiting traffic to one lane in each direction. Flaggers, traffic cones, and traffic signage will be used to direct vehicles and pedestrians during construction. Area residents, businesses and the travelling public can expect traffic delays along with some construction noise, vibration and dust in and around work areas.
No local business closures are expected during construction, and full pedestrian and vehicle access will be maintained during regular business hours.

Hours

  • Monday - Friday, 7 a.m. - 7 p.m.

Schedule

Construction will be done in stages, so not all areas will be under construction at the same time. Work will generally progress from south to north along Everett St. to Leadbetter Rd., where it will continue west along Leadbetter Rd., through Camp Currie and terminate near the intersection of Goodwin Rd and Ingle Rd. A new waterline will also be constructed as part of the project starting near Camas High School, running west on NE 43rd Ave, crossing Everett St. and then continuing along Leadbetter Rd. to the new Lacamas Lake Elementary School. Construction is expected to be complete by May 2018.

 

Activities

Example of open trench construction.

The project will primarily use an “open cut” or “open trench” construction technique to install the new pipeline. Trench boxes and sheeting will provide vertical shoring for trench walls to minimize the necessary width of the excavation and to protect the crews working in the trench. This approach also minimizes utility and traffic impacts. In most areas the pipeline trench will occur in the center of the roadway, requiring the closure of one lane of traffic. After construction, excavated trench areas will be backfilled and the pavement restored to allow normal vehicle movement.


Project Contacts

  • For questions, more information, or to join the interested parties list, you can contact a member of the project team at northshore@cityofcamas.us or by calling 360-817- 7377.
  • You can also download the City's Mobile app CamasConnect for Android or iPhone, or like us on Facebook or Twitter for up-to-date news on the project.

Mayor's Blog

Native RTL SupportMAYORS BLOG GOES HERE

My Camas
Go to top